Meta: Implementation Roadmap #17

Open

Description

@ggondim

Dependency Graph

#1 Bootstrap
 └─► #2 Data Model & Interfaces
      ├─► #3 Router ──────────────────┐
      ├─► #4 Reply Engine ◄───────────┤
      ├─► #5 Token & Thread Mgmt ─────┤
      ├─► #6 MongoDB Adapter ─────────┤
      ├─► #7 Slack Adapter ───────────┤
      ├─► #8 Telegram Adapter         │
      ├─► #9 Discord Adapter          │
      └─► #10 WhatsApp Adapter        │
                                      ▼
                              #11 Server: API Routes
                               ├─► #12 A2H Forms
                               │    └─► #14 Trust Layer
                               ├─► #13 Dashboard UI
                               └─► #15 Integration Testing
                                    └─► #16 Release & DX

Execution Order

Issues grouped by wave — all issues within a wave can run in parallel.

Wave 1 — Foundation

Wave 2 — Contracts

Wave 3 — Core Logic + Adapters (parallel)

Wave 4 — Reply Engine

Wave 5 — Server + More Adapters (parallel)

Wave 6 — UI & Forms (parallel)

Wave 7 — Trust & Hardening

Wave 8 — Release

Orchestrator Instructions

When picking the next issue to enqueue:

  1. Issues within the same wave can be assigned in parallel
  2. A wave is ready when ALL issues from previous waves are checked
  3. An individual issue is ready when ALL its explicit dependencies (listed in its body) are checked
  4. After completing all issues, open a final PR: meta/<this_issue_number> → main

Activity

  1. added
    metaOrchestration meta issue for implementation plans
    on Apr 10, 2026
  2. ggondim commented on Apr 10, 2026

    @ggondim
    ContributorAuthor

    @claude Start the orchestration loop. Read this meta issue, create the meta branch, and assign the first wave of tasks.

  3. ggondim commented on Apr 10, 2026

    @ggondim
    ContributorAuthor

    @claude Start the orchestration loop. Read this meta issue, create the meta branch, and assign the first wave of tasks.

  4. ggondim commented on Apr 10, 2026

    @ggondim
    ContributorAuthor

    @claude Start the orchestration loop. Read this meta issue, create the meta/17 branch, and assign the first wave of tasks.

  5. ggondim commented on Apr 10, 2026

    @ggondim
    ContributorAuthor

    @claude Start the orchestration loop. Read this meta issue, create the meta/17 branch, and assign the first wave of tasks.

  6. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Setup

    • Created branch meta/17 from main ✓

    Issues Marked Done

    • None yet (all unchecked)

    Issues Assigned

    What's Next

    Once #1 is merged, Wave 2 becomes ready:

    After #2 merges, Wave 3 (parallel) becomes ready:

  7. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked Done

    Assigned

    What's Next

    Issue #2 is the Wave 2 blocker. Once it merges, Wave 3 issues (#3, #5, #6, #7) can all run in parallel.

  8. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked as done

    Assigned (Wave 3 — all parallel, all P0)

    What's next

    Wave 3 is now in progress. Once all four issues are merged:

  9. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked Done

    Assigned (Wave 3 — parallel)

    All three have priority:P0 and auto-merge enabled:

    What's Next

  10. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked done

    Already in progress (assigned earlier)

    Newly assigned

    What's next

    Wave 4 (#4) is now unblocked and in progress. Wave 3 (#6, #7) are still in progress. Once #4, #6, and #7 are all merged, Wave 5 (#8, #9, #10, #11) will become ready.

  11. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked Done

    Assigned (Re-triggered)

    Newly Assigned

    Blocked (waiting on dependencies)

    Current Wave 3/4 Progress

    Issue Status
    #3 Router ✅ Done
    #5 Token & Thread Mgmt ✅ Done
    #6 MongoDB Adapter ✅ Done
    #7 Slack Adapter 🔄 In progress
    #4 Reply Engine 🔄 In progress
  12. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked as done

    Assigned

    What's next

    Wave 4 (#4 Reply Engine) is now in progress. Once #4 merges, Wave 5 will unlock: #11 (Server: API Routes, P0), #8 (Telegram, P1), #9 (Discord, P2), #10 (WhatsApp, P2) — all can run in parallel.

    Blocked

    All other waves are waiting on Wave 4 to complete.

  13. ggondim commented on Apr 10, 2026

    @ggondim
    ContributorAuthor

    @claude Continue the orchestration loop. Check for merged PRs and assign the next wave.

  14. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked Done

    Wave 5 Assigned (all in parallel)

    What's Next

    Once all Wave 5 issues are merged, Wave 6 will begin:

  15. ggondim commented on Apr 10, 2026

    @ggondim
    ContributorAuthor

    @claude Continue. Check all merged PRs, update checkboxes, and assign the next wave.

  16. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked as Done (Wave 5 complete)

    Assigned (Wave 6 — parallel)

    What's Next

    Once both #12 and #13 are merged into meta/17, Wave 7 will begin:

  17. github-actions commented on Apr 10, 2026

    @github-actions
    Contributor

    ⚠️ Meta Orchestrator Failed

  18. github-actions commented on Apr 10, 2026

    @github-actions
    Contributor

    ⚠️ Task Worker Failed — Issue #12

  19. github-actions commented on Apr 10, 2026

    @github-actions
    Contributor

    ⚠️ Task Worker Failed — Issue #13

  20. github-actions commented on Apr 10, 2026

    @github-actions
    Contributor

    ❌ Fix agent failed on issue #13. View run — Manual intervention needed.

  21. ggondim commented on Apr 10, 2026

    @ggondim
    ContributorAuthor

    @claude Continue. Check all merged PRs, update checkboxes, and assign Wave 7.

  22. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked Done

    Assigned (Wave 7 — Trust & Hardening)

    Both Wave 6 issues are now complete, unlocking Wave 7. Issues #14 and #15 can proceed in parallel.

    What's Next

    After #14 and #15 are merged → Wave 8: #16 Release & DX (P3) becomes ready.

  23. ggondim commented on Apr 10, 2026

    @ggondim
    ContributorAuthor

    @claude Continue. Mark Wave 7 as done and assign Wave 8.

  24. claude commented on Apr 10, 2026

    @claude

    Orchestrator Update

    Marked as Done

    Assigned

    What's Next

    Wave 8 (#16) is now in progress. Once #16 is merged, I will open the final PR from meta/17 → main to complete the implementation roadmap.

  25. ggondim commented on Apr 11, 2026

    @ggondim
    ContributorAuthor

    @claude All Wave 8 issues are merged. Mark them done and open the final PR from meta/17 to main.

  26. claude commented on Apr 11, 2026

    @claude

    Orchestrator Update — All Issues Complete

    Marked Done

    All Waves Complete

    Every issue across all 8 waves is now checked:

    Wave Issues Status
    Wave 1 — Foundation #1 ✅
    Wave 2 — Contracts #2 ✅
    Wave 3 — Core Logic + Adapters #3, #5, #6, #7 ✅
    Wave 4 — Reply Engine #4 ✅
    Wave 5 — Server + More Adapters #11, #8, #9, #10 ✅
    Wave 6 — UI & Forms #12, #13 ✅
    Wave 7 — Trust & Hardening #14, #15 ✅
    Wave 8 — Release #16 ✅

    Final PR Opened

    PR #34 has been opened to merge meta/17 → main with a full summary of everything implemented.

    No further issues to assign. The roadmap is complete! 🎉

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Metadata

Metadata

Assignees

No one assigned

    Labels

    metaOrchestration meta issue for implementation plans

    Type

    No type

    Projects

    No projects

      Milestone

      No milestone

      Relationships

      None yet

      Development

      No branches or pull requests

      Issue actions