feat(wasserfoerderung): FI 5.008 planner engine with per-pump pressures #584
Slice 1 of the Wasserförderung restart (#150). Domain only — no UI, no persistence, no sync. Analysis and rationale: see the review comment on #150.
Why
The planner on feat/wasserfoerderung-plan-a (FörderstreckePlanner) has problems in its hydraulics:
Its friction table is optimistic compared with FI 5.008 Tab. 3: 1,0 vs. 1,2 bar/100 m at 800 l/min. At 8 bar / 1,5 bar it plans a 620 m flat leg where FI 5.008 Abb. 22 gives 540 m, so pumps end up ~15 % too far apart.
On a descent Cost() goes negative and the leg keeps extending. Nothing checks overpressure against the B hose's 16 bar.
It returns only counts and positions in metres. There are no per-pump pressures.
The reserve is a unitless "3 % of budget" instead of a pressure in bar.
Scope
Friction per FI 5.008 Tab. 3 (600/800/1000/1200 l/min), cited in the code.
Inputs: Förderstrom, pump type / Ausgangsdruck (8 or 10 bar), min. Eingangsdruck, Sicherheitsreserve in bar, Warnschwelle, optional Einsatzstellenpumpe at the target.
Input profile as Stützpunkte (Strecke m, Höhe m), interpolated to 20 m stations. Keep the branch's worst-interior-point crest check.
Result per pump: role (Wasserentnahmestelle / Verstärkerpumpe / Einsatzstellenpumpe), station, Höhe, Eingangsdruck, Ausgangsdruck, section length / rise / B-20 count.
Typed findings instead of exceptions where the plan is still usable: overpressure downhill, a segment that cannot be pumped at all, Restdruck at the target below the minimum, >1000 l/min → Doppelleitung.
A partial last segment is charged pro rata, not as a full 20 m. Hose totals equal the sum of the sections.
Out of scope / open
Offene Schaltreihe: model it correctly (every pump draws from a Faltbehälter) or leave it out. Re-checking only the last stretch is not enough.
The DBV setting, reserve pump ratio and reserve hose rule need a cited source before they are shown as instructions.
Acceptance
Golden tests reproduce FI 5.008 Abb. 22 (0/540/920/1260 m, 0/0/19,2/43,2 m, 8 bar, 800 l/min) and Abb. 23 (0/458/579 m, 0/14/19 m).
Tests cover a downhill overpressure case, an infeasible steep segment, a route shorter than one hose, and a partial last segment.